Synchronizing the Project¶
The synchronization updates the metadata necessary to include in the smart view the information provided by functionalities and the data sources that you have selected during the project configuration. In short, the project synchronization transforms the data of the manufacturing data warehouse into measures and attributes that you can use in your analysis. The progress of this operation is tracked on the "Monitoring Messages" page.
A measure is created only if the values for that measure exist. For example, a measure for counters is created only if values for those counters have been transferred to the MDW. The same example can be applied to measures for speed.
Prerequisites¶
- You have created and configured the Project, the Scenario and the Environment.
- You have performed a deploy of the Environment and an initial Flow to load data.
Limitations¶
- When you synchronize the project in the "Smart Views" page, for the entities with a hierarchy (like for example Equipment, OperationExecution, OperationResponse etc.) the hierarchy might generate a loop (for example, Equipment1 → Equipment2 → Equipment1). In that case, in the "Attributes" cards of the smart view the levels cannot be selected for that entity.
- A limitation has been introduced for smart view project synchronization. During the project synchronization process, some measures and attributes are created based on the data that are ingested from the data sources. Examples of data that are generating measure or attributes are counters (indicators), quality parameters, properties, etc. In this case, a very high number of measures and attributes may be generated. If there are too many measures or attributes, the Measures and Attributes pages might not be able to load and display them. This is typically due to particular configurations of the source application’s project that cause this issue. Therefore, to avoid page loading and display problems, a limitation has been introduced so that no more than 200 measures or 200 attributes can be generated per each section of each single card. If their number exceeds 200, the first 200 are displayed in alphabetical order. In the case of properties, which can be both measures and attributes, the limit of 200 is applied to the total number of properties. For example, if there are 200 numeric properties and 200 text properties, the first 100 numeric properties and the first 100 text properties are displayed in alphabetical order. If their quantities are highly asymmetric, for example 200 numeric properties and 2 text properties, the first 198 numeric properties and the 2 text properties are displayed.
Procedure¶
- On the "Smart View" page, click "Synchronize Project".
- In the "Projects" drop-down list, select the Project.
- In the "Environment" drop-down list, select the Environment.
- Click "Synchronize".
- In the "Monitoring Messages" page, monitor the progress and completion of the operation.