Creating a standard KPI¶
If you have selected the Standard type KPI, you can select a predefined KPI formula from the ISO 22400-2 standard. You then need to map each formula element to the corresponding real measures defined in the smart view for which the KPI is being created. You will also be able to add filters and grouping criteria to standard KPIs, as well as modify the mapping between its elements and the smart view measures but you will not be allowed to modify the formula. To make line or plant supervisors aware about the status of the KPIs - whether they are on-target or out-of-target in a prescribed time, the concept of absolute or time-related target input is required.
The KPIs defined in this section are used at runtime for calculating KPI results using the Calculate KPI Results API. KPIs are only displayed in List mode in order of creation.
Important recommendations¶
- When you delete a smart view on whose measures, attributes or contexts a Custom or Standard KPI is based, the KPI is also deleted. If you create a new smart view, you can create Custom and Standard KPIs with the same name as the name of the KPI name related to the deleted smart view.
- If a KPI is used in a KPI event, the KPI cannot be deleted.
Prerequisites¶
You have created a smart view and selected a number of measures and attributes in the corresponding pages.
Procedure¶
- In the KPI tab, click "Create KPI".
- Select the "Standard" type checkbox.
- Select a standard KPI from the drop-down menu: the name and description fields are automatically filled with details on the selected KPI. For the available KPIs the required measures are available in the model or can be added by means of extensions. For more details, see "Supported ISO 22400-2 standard KPI formulas".
- In the "Unit of Measurement" field, type the required unit of measurement for the KPI you want to create. The length of this field must not exceed 200 characters. The reverse slash or escape key is not allowed as an input value.
- In the "Value Type" drop-down menu, select "Real" or "Integer". The limits, targets, and KPI results are rounded off to the nearest integer value when the Value Type option is Integer.
- (Optional) If you want to define the KPI result range, insert the minimum value of that range in the "Minimum Value" field.
- (Optional) If you have inserted the minimum value, you must insert the maximum value of the KPI result range in the "Maximum Value" field. The maximum value must be greater than the minimum value. The "Save" button is enabled if no values are entered in Minimum Value and Maximum Value fields or if values in a correct format have been inserted for both options.
- From the "Target Type" drop-down menu, select one of the available options and enter their respective values (see table below).
- To define the time quotient for KPIs, select the "Time related limits/target", and set the following:
- "Unit of Time": (Minutes, Hours or Days).
- "Time Value": enter a numeric value.
- Click "Save".
| Target Type | Target Value | Target Criteria Options |
|---|---|---|
| Single Target | Target Value | KPI is on Target if: KPI Value \<= Target ValueKPI Value >= Target Value |
| No Target | None | None. For this target type, target criteria options and target values are not displayed. |
| Double Target | Low Target ValueHigh Target Value | KPI is on Target if: KPI Value >= High TargetKPI Value \<= Low TargetLow Target \<= KPI Value \<= High Target |
Mapping standard KPI elements with measures¶
- In the "KPI" tab, select a standard KPI and click "Open".
- In the KPI Editor, select an element of the formula.
- To replace the element in the Toolbox, click on the measure you want to replace it with.
- To map more than one measure on the same element, click "Append Measures" and then on the required measures.
- Click "Save".