OEE Standard Formulas¶
OEE formula
Availability related formula
The sum of downtimes is determined through different machine states and the underlying time model.
Performance related formulas
Theoretical Output depends on the currently produced products in the selected time range. If different products are produced in the selected time range, then the Theoretical Output is the sum of the different time ranges for which the product has been produced multiplied by the product individual design speed.
The number of total parts must be collected.
Quality related formulas
As shown in the formula above, two out of the three parameters (Total Parts, Good Parts, Rejected Parts) must always be collected. The third variable can always be calculated based on the other two variables.
Miscellaneous formulas¶
Mean Time To Repair
Mean Time Between Failure
TEEP